Beacon Wins Alberta’s Second Major Data Centre Power Plant Approval

Alberta regulators have approved a 920-MW natural gas power plant for Beacon Data Centers northeast of Edmonton, marking the province’s second major approval this year for a near-gigawatt-scale power facility serving an AI data centre.

The Alberta Utilities Commission’s Oct. 23 decision advances Beacon’s proposed 800-MW campus in Sturgeon County, featuring four buildings for artificial intelligence and high-performance computing.

The development is planned for a 320-acre industrial-zoned property near Highway 643 and Range Road 223, about seven kilometres east of Gibbons. The power plant would occupy 32 acres of the site and use 200 natural gas generators.

Sturgeon County issued a site-grading permit Oct. 22, one day before the provincial approval. Beacon is targeting initial operations in late 2027.

Calgary-based Beacon was established in 2023 and is pursuing more than 10 data centre projects across North America, representing over 6,000 MW of planned capacity.

The company is part of a much larger development wave. Alberta Data Centre Watch tracks 45 active data centre projects across the province, including 21 with published plans for dedicated power generation totalling 8.4 GW. Not all have submitted formal applications to the AUC.

Beacon’s approval follows the commission’s June authorization of the 1,864-MW Greenlight Electricity Centre, planned in two phases to support Meta’s $13B data centre in Sturgeon County. The first phase involves 932 MW of generating capacity.

But not every proposal has succeeded.

In August, the AUC rejected a 1,400-MW natural gas plant for Synapse’s proposed $10B data centre in Olds, finding the facility too close to surrounding neighbourhoods.

Beacon is also awaiting a decision on a separate 1,494-MW power plant near Indus, east of Calgary, intended to serve another proposed data centre campus.

The Heartland approval covers electricity generation, not the data centre itself, which remains subject to other development requirements.

Connect

Inside The Story

About Joel Bowey

Joel Bowey is Director of Content and Events for Connect CRE in Canada, leading the company’s editorial coverage and industry engagement across the Canadian commercial real estate market. He brings more than 20 years of experience in Canadian journalism and digital media, including senior leadership roles with CTV News, CP24 and BNN Bloomberg. Most recently, he served as Senior Managing Editor at Bell Media, overseeing major newsrooms, national coverage and digital growth initiatives. Throughout his career, Joel has led large editorial teams, covered major Canadian business and economic stories, and helped develop new audiences across platforms. At Connect CRE, he is focused on delivering timely, useful reporting on the people, projects, deals and trends shaping commercial real estate in Canada. Based in the Greater Toronto Area, Joel also represents Connect CRE at industry events and conferences across the country.