Bell’s Saskatchewan AI Data Centre Construction Scales Up
More than 500 workers are now building Bell’s 300-MW AI data-centre campus outside Regina, where structural steel is rising on all four first-phase buildings and the first is being prepared for interior construction.
Bell disclosed the milestones during an Oct. 1 update at the 65-hectare site in the Rural Municipality of Sherwood. The first data halls remain scheduled to begin operating in the first half of 2027.
Unlike many of the enormous AI data-centre projects being proposed across Canada, Bell is not building on speculation. The full initial 300 MW is contracted under long-term agreements with Cerebras and CoreWeave. Bell is investing about $1.7B in the land, buildings, power, cooling and connectivity infrastructure, while the tenants fund and install their computing hardware.
The activity puts Sherwood alongside Meta’s 1-GW campus under construction in Sturgeon County, Alta., among the major Canadian AI developments that have advanced from announcements to large-scale construction.
Bird Construction is managing the Sherwood build, with more than 30 local contractors, consultants and suppliers involved. Dynamo Electric is building the high-voltage substation connecting the campus to SaskPower.
The impact is also moving beyond the site. Regina Mayor Chad Bachynski said the construction workforce is generating business for local hotels, restaurants and service providers. Bell also plans to establish its AI Fabric headquarters in Regina, bringing up to 100 management positions to the city, although an office location has not been announced.
Bell last month outlined plans that could expand its Saskatchewan AI infrastructure to 1.2 GW, potentially taking associated investment to $52.5B.
Join Us | Connect Alternative Real Estate Investments comes to Vancouver on Oct. 15, bringing together investors, owners, developers and lenders to examine where alternative real estate is working, how deals are getting financed and what comes next for B.C. CRE. The program covers seniors housing, student housing, self-storage and other specialized assets, along with the policy, capital and development issues shaping the market. Register here.