Ontario Targets 80% Cut In Archaeological Approval Times
Ontario is proposing a major overhaul of archaeological approvals that could shave months or even years off development timelines, removing a potential obstacle for housing, industrial and infrastructure projects.
The province announced proposed legislative changes Tuesday aimed at reducing archaeological approval timelines by an average of 80% while increasing assessment capacity by 45%.
Under the current four-stage system, archaeological assessments can take up to 64 months to complete. The province received 3,800 assessment reports for regulatory review in 2025, reflecting growing demand as developers seek to advance projects.
The proposed reforms would streamline reviews for lower-risk developments, introduce exemptions for certain small-scale residential projects and eliminate unnecessary licensing requirements. Improved digital mapping and integration with Ontario’s centralized permitting system are also planned.
“By cutting approval timelines by up to 80 per cent, we’re helping get homes and infrastructure built sooner,” said Graham McGregor, Ontario’s minister of citizenship and multiculturalism.
The government says it has already cleared a backlog of more than 3,000 archaeological reports.
Implementation would begin in early 2027, with further changes developed through consultation with Indigenous communities and industry stakeholders.